Hong visits Nakdong Tunnel 1 on Friday, orders smooth partial opening in April

Land, Infrastructure and Transport Minister Hong Ji-seon visits the Bujeon-Masan double-track railway construction site on Friday, urging all-out efforts to advance the full opening of the line, which has been delayed more than five years following a tunnel collapse.
Land, Infrastructure and Transport Minister Hong Ji-seon visits the Bujeon-Masan double-track railway construction site on Friday, urging all-out efforts to advance the full opening of the line, which has been delayed more than five years following a tunnel collapse.

Land, Infrastructure and Transport Minister Hong Ji-seon visited the Bujeon-Masan double-track railway construction site — delayed more than five years by a collapse accident — and called on project operators to make every effort to advance the full opening of the line as soon as possible. Hong also urged them to ensure the planned partial opening in April next year proceeds without a hitch.

The Ministry of Land, Infrastructure and Transport said Hong visited the construction site Friday afternoon to review the project's progress.

Walking through the 3.2-kilometer Nakdong Tunnel 1, Hong said the opening had been delayed due to incomplete emergency connecting passages but that the project had now reached a turning point. "The ministry will actively support safe construction through its advisory council and make every effort toward an early full opening," Hong said. Hong also told the project operator that there must be no lapse in safety management for the remaining work, and urged the operator to do everything possible to advance the full opening for residents who have endured inconvenience for a long time.

The Bujeon-Masan double-track railway is a build-transfer-lease private investment project that lays 32.7 kilometers of new track from Bujeon in Busan to Jinrye in Gimhae, with train service between Bujeon and Masan to follow upon completion. A collapse in March 2020 delayed the opening by more than five years, and restoration work on the collapsed section was completed in January this year. Following the release of findings by the Construction Accident Investigation Committee on Nov. 19, the ministry said it would work with the project operator to resume the remaining suspended construction and push together for an early full opening.

Hong received briefings Friday from Smart Rail, the project operator, and Korea Railroad Corporation, the operating agency, on plans for the partial opening. Hong urged both parties to carry out all remaining procedures without delay and to draw up a detailed train service plan so that residents who have long awaited the opening can begin using the line in April next year. Hong also personally inspected the restored section of Nakdong Tunnel 1 and said that, with the restoration work now complete despite difficult conditions, facility management must be thorough so the public can use the line with confidence.

Earlier Friday morning, Hong visited the Bansong-Banyeo policy relocation district in Haeundae-gu, Busan, to examine aging housing and residents' living conditions. Hong also discussed ways to improve the residential environment with Busan city, Haeundae-gu and Korea Land and Housing Corporation (LH). The Bansong-Banyeo district was established in the 1960s and 1970s to house residents displaced when substandard hillside housing in central Busan was demolished. Hong said the ministry would work with LH to survey the formation and current conditions of policy relocation districts nationwide and seek effective measures to improve living conditions so residents can enjoy a better environment.