Bidding and review periods shortened
Contract and ground-breaking preparations to run in parallel
Korea Land and Housing Corporation (LH) announced Thursday it has drawn up and will implement a plan to accelerate the entire process from procurement to contract signing and ground-breaking.
The plan is designed to move up the housing supply schedule in line with the government's "rapid housing supply measures" announced Aug. 13, cutting the time required at each stage from procurement planning to ground-breaking to support earlier construction starts. In that package, the government said it would supply more than 230,000 additional housing units in the Greater Seoul area through LH.
LH will first overhaul its workflow by working backward from scheduled ground-breaking dates to set procurement timelines. Going beyond simply managing schedules up to contract signing, the corporation will strengthen advance coordination between procurement departments and contract and review teams, centering on the actual ground-breaking date, so that each step follows the next without delay.
For projects requiring emergency procurement to implement housing supply policy, LH will make active use of emergency bidding and minimize delays caused by failed bids, corrections and re-announcements through advance reviews of procurement requests and early notification of ground-breaking plans. The corporation also plans to work closely with contractors to run contract signing and ground-breaking preparations simultaneously, reducing the waiting period between contract award and construction start.
Through these measures, the time from procurement planning to ground-breaking for construction projects subject to the comprehensive evaluation award system — including site development works valued at 30 billion won ($22.4 million) or more — will be cut by 67 days, from 130 days to 63 days.
Key improvements include skipping the advance public disclosure of procurement plans by incorporating them into annual planning, and issuing emergency bid notices. The site briefing and cost-estimation period will be cut by 32 days — from 34 days to two — by eliminating on-site briefings, and internal review schedules for pre-qualification and comprehensive evaluation will also be shortened. At the contract stage, contract signing and ground-breaking preparations will proceed in parallel so that construction can begin immediately upon completion of all related procedures.
Projects valued at under 30 billion won will also benefit from streamlined procedures, including emergency bidding and shorter review schedules. For works between 10 billion won and 30 billion won subject to the simplified comprehensive evaluation award system, the timeline will be cut by 48 days, from 105 to 57 days. For works under 10 billion won subject to qualification review, the reduction will be 55 days, from 98 to 43 days.
Emergency bidding will also be applied to technical service contracts related to housing supply — such as surveying and appraisal — as well as general service contracts covering research and project support, to accelerate related procurement.
LH has also concluded consultations with the Public Procurement Service to allow emergency bidding for public housing design, construction and supervision work handled by that agency when needed for housing supply policy implementation. The corporation has completed emergency bid requests for all 38 projects slated for ground-breaking this year, totaling about 5.4 trillion won.
"Ensuring the government's rapid supply policy is carried out without a hitch to stabilize the housing market is the corporation's top priority," LH President Lee Seong-hun said. "We will innovate the entire process — from procurement and contracting to ground-breaking — to break ground on housing earlier and deliver housing supply results that people can feel."