Results of regular audit of Jeju Island released

Discipline sought for official in charge

Ministry notified to consider cutting local allocation tax

Board of Audit and Inspection
Board of Audit and Inspection

Jeju pressed ahead with a road widening and paving project despite twice failing investment reviews, an audit by the Board of Audit and Inspection has found. A civil servant overseeing the project was also found to have ordered the work signed off as complete even after being told the contractor had not conducted required quality tests.

The Board of Audit and Inspection released the findings Wednesday as part of its regular audit of Jeju Special Self-Governing Province.

According to the audit, Jeju signed a contract in June 2022 to widen and pave a section of County Road 71, which runs 5 kilometers in total, and completed the work in April last year.

The project had previously been rejected twice — in August 2019 and March 2021 — by Jeju Island's investment review committee, which found it lacked urgency and viability and raised concerns about environmental damage.

Under relevant regulations, new investment projects with a total budget of between 4 billion won and 30 billion won ($2.96 million-$22.3 million) are required to undergo an investment review by Jeju Island.

Jeju circumvented that requirement by shortening the construction section from 1.5 kilometers to 1.1 kilometers and trimming the total project cost from 4.14 billion won to 3.98 billion won, allowing it to proceed without a separate investment review.

The auditors said the move resulted in wasteful spending: the remaining 3.9 kilometers of unpaved road on the same route went unused by vehicles, leaving the road unable to function as intended.

Problems also emerged in how the construction was supervised and approved for completion.

The Grade-6 civil servant who headed the project team at Jeju was informed by the construction supervisor that the contractor had not carried out quality tests as outlined in a previously submitted testing plan. Despite this, the official did not call for corrective measures such as quality testing or rework, and instead directed that the project be processed as complete.

In fact, when auditors conducted sample inspections of three asphalt-paved sections during the audit period, two fell below quality standards for asphalt compaction thickness and compaction rate.

The Board of Audit and Inspection called on the Jeju mayor to discipline the official for negligence in handling the completion process, and issued caution notices to two others involved. It also notified the relevant parties to assess the extent of the contractor's substandard work and take appropriate remedial action, including supplementary construction.

The Ministry of Interior and Safety was notified to consider reducing local allocation tax grants to Jeju Special Self-Governing Province and take other appropriate measures in response to Jeju's decision to proceed with the project in defiance of the investment review outcome.

The board said it conducted the audit because Jeju Special Self-Governing Province, while granted considerable authority over fiscal and personnel matters under the Special Act on Jeju, had not been audited since 2019, making a review of local fiscal projects, construction safety management and employee conduct management necessary.