Contracts cover a 1,050 MW cogeneration plant in Yongin, Gyeonggi Province,
and an LNG combined-cycle plant in South Jeolla Province
Hyundai Engineering announced Wednesday that it has secured two consecutive power generation contracts totaling about 2.28 trillion won ($1.7 billion).
The company signed a contract worth approximately 1.65 trillion won with Yongin Cogeneration — a joint venture established by Korea Midland Power and SK Innovation E&S — to build the Yongin cogeneration power plant, and has begun work on the project. It separately signed a contract worth about 630 billion won with Korea East-West Power to build the Honam combined-cycle power plant.
The deals come after Hyundai Engineering was named the preferred bidder for both projects in September, with the company swiftly completing negotiations with project owners and consortium partners to finalize the contracts.
The Yongin cogeneration power plant project involves constructing a 1,050 MW electricity generation facility and a 517 gigacalorie (Gcal)/h heat production facility within the SK hynix semiconductor industrial complex in Cheoin-gu, Yongin, Gyeonggi Province. Hyundai Engineering will oversee the full engineering, procurement and construction (EPC) scope, with completion targeted for September 2030.
The plant is a large-scale energy supply facility designed to meet the heat and steam demands of semiconductor factories. Once completed, the electricity and thermal energy it produces will strengthen the energy supply foundation of the Yongin SK semiconductor cluster, a key hub driving the growth of the country's advanced industries.
The Honam combined-cycle power plant project involves building a 500 MW LNG combined-cycle power plant on the site of the former Honam thermal power plant within the Yeosu National Industrial Complex in South Jeolla Province. Hyundai Engineering will serve as the consortium lead, handling design and procurement of major equipment, while Posco E&C will carry out construction. The plant is scheduled to break ground in June 2027 and be completed in May 2030, after which it is expected to contribute to stable power supply in the Honam region, including the Yeosu National Industrial Complex.
With these contracts, Hyundai Engineering said it has secured a foothold in power generation at major industrial hubs in the greater Seoul area and the Honam region. The company plans to expand its participation in nearby power infrastructure projects while also moving into next-generation energy sectors such as hydrogen power and small modular reactors.
"Signing back-to-back main contracts within about two months of being named preferred bidder again confirms the trust placed in Hyundai Engineering's technical capabilities and project execution," a company official said. "We will successfully carry out both projects to contribute to a stable power supply and continue strengthening our competitiveness as a key player driving the evolution of the energy value chain."
Meanwhile, Hyundai Engineering's cumulative operating profit through the third quarter of this year surpassed its full-year operating profit for last year, and new orders more than doubled compared with the same period a year earlier. The company also climbed from sixth to fourth in this year's construction capability assessment rankings.
hss@heraldcorp.com