City raises budget and extends timeline to 2030 to ensure faithful restoration; forecourt to open to public in March

The former Daejeon Public Hall, built in 1937.
The former Daejeon Public Hall, built in 1937.

The restoration and repair of the former Daejeon Public Hall — built in 1937 as the Daejeon prefectural office — will resume after facing the prospect of a full review or suspension under the current city administration due to tight fiscal conditions.

Daejeon city said Wednesday it had adjusted its plans to continue the project, citing the building's historical and architectural significance, its prime location in the heart of the old city center, and its potential for diverse public use.

The former Daejeon Public Hall completed its advance notice period for registration as a national registered cultural heritage from Oct. 12 to Nov. 11, with a final decision on registration expected before the end of the year. The city plans to standardize the building's name to "former Daejeon Public Hall" — its official registered designation — replacing the various names it has been known by, such as "Daejeon prefectural office" and "first Daejeon City Hall," and will reflect the new name in the project title as well.

Once national heritage registration is confirmed, the project will be reclassified as an official national heritage repair and maintenance undertaking, placing greater emphasis on preserving the building's original form and historical value. The city plans to finalize its restoration and repair plan based on rigorous historical research and expert consultation, then proceed to main construction after obtaining the necessary permits and design approval from the Cultural Heritage Administration.

The total project budget will increase by 12.4 billion won ($9.21 million) from the original 44 billion won to 56.4 billion won, as the scope of work is refined to address preservation and future use requirements. The figure includes 34.2 billion won in acquisition costs; the remaining 22.2 billion won covers restoration, repair and the creation of public-use facilities.

The additional funding will go toward preserving original structural elements newly uncovered after interior finishing materials were removed and creating spaces that are safe for public use. It will also cover repairing and conserving architectural features from the time of construction, reinforcing structural safety — including seismic upgrades identified during the design process — and remodeling for public programming.

Interior surveys have revealed a number of significant original architectural features, including a coffered ceiling in the third-floor grand hall, wooden floor tiles on the second floor, and decorative ceiling moldings. The city said it considers these important evidence of the building's historical and architectural value, and plans to preserve as much as possible through thorough investigation, historical verification and expert review before proceeding with restoration and repair.

To carry out this preservation and restoration process faithfully, the project completion date has been pushed back from the original target of late 2028 to the second half of 2030. The extension reflects additional administrative steps required — including a feasibility study, a permit for changes to the registered heritage site, and design approval — but the city said the timeline was fundamentally set to allow sufficient time to uphold the principles of restoring a significant architectural heritage.

Rather than rushing to shorten the construction period, the city said it will prioritize construction safety and restoration quality through thorough historical research and careful execution.

Alongside preserving the building's original form, the city is also preparing discussions on how citizens will use the space after restoration is complete. It plans to revisit an earlier proposal that emphasized commercial use — including attracting private businesses and establishing local brand shops — and instead strengthen the public character of the space in line with the current city administration's policy direction and citizens' cultural needs. A specific use plan will be developed through consultation with the cultural heritage committee, public opinion gathering, a policy advisory panel and relevant city departments, with an announcement expected around March to April next year.

To allow citizens to use the site while those discussions and restoration preparations are underway, the city will open the forecourt before main construction begins. Construction barriers will be removed and the area prepared as a space for rest and cultural events, with the opening — tentatively named "Heritage Space 1937: Time Waiting for the Daejeon Public Hall" — set for March next year.

The space will operate as a pocket park serving the old city center, which lacks green space, on regular days, and as a cultural venue for busking, pop-up exhibitions and flea markets on weekends and special occasions. The forecourt will open first, while the city reviews the procedures and costs for a change of use under building regulations before deciding whether to open the first floor of the building as well.

"Restoring the former Daejeon Public Hall means reclaiming a historic space in our city and returning it to the lives of our citizens, so we will pursue this with thorough historical research, careful construction and the support of the public," Daejeon Mayor Heo Tae-jeong said. "Rather than treating the time until completion as simply a waiting period, we will make it a time for citizens to enjoy the space first and discover its value together."