Verification required when 20% of members demand it

Associations must apply within 30 days amid rising cost disputes

A construction site in downtown Seoul. [Herald DB]
A construction site in downtown Seoul. [Herald DB]

A mandatory construction cost verification regime will be extended to housing associations and apartment remodeling projects starting next year.

The Ministry of Land, Infrastructure and Transport announced Friday that it had issued a pre-announcement of legislation on the "Standards for Construction Cost Verification for Housing Association Projects and Similar Developments."

The measure follows an amendment to the Housing Act passed in September and takes effect March 9 next year. It expands the mandatory construction cost verification requirement — previously limited to reconstruction and redevelopment projects — to cover housing associations and apartment remodeling projects as well.

Under the amended law, if at least one-fifth, or 20 percent, of association members or apartment owners request a review, the association must submit a construction cost verification request to an accredited body such as the Korea Real Estate Board.

Even without a member request, verification is required when construction costs rise by 10 percent or more if a contractor was selected before project plan approval, or by 5 percent or more if selected after approval. Cases where costs increase by a further 3 percent or more following a completed verification are also subject to the requirement. Producer price inflation is excluded when calculating the rate of cost increases.

Once triggered — either by a petition from at least one-fifth of members or by a cost increase exceeding the applicable threshold — the association must apply for verification within 30 days. The verifying body must then deliver its findings within 60 to 75 days of receiving the application, depending on the scale of the costs involved.

Associations that selected a contractor before the regime takes effect will calculate their cost increase rate based on the contract amount in place immediately before March 9 next year.

However, where an association has already agreed to a cost increase and signed an amended contract before the system launches, the practical effect of verification may be limited. Even if the verifying body determines an appropriate cost figure, contractors are not legally obligated to revise the contract to match that amount.

The mandatory construction cost verification system was first introduced for reconstruction and redevelopment projects in 2019, but housing associations and apartment remodeling projects governed by the Housing Act were not subject to the same requirement. The government decided to apply identical verification standards to these projects to give them a comparable mechanism for resolving disputes over cost increases.

Meanwhile, data on construction cost verification for redevelopment and reconstruction projects obtained by Rep. Bok Gi-wang of the Democratic Party of Korea, a member of the National Assembly's Land, Infrastructure and Transport Committee, from the Korea Real Estate Board showed that of 166 reconstruction and redevelopment sites reviewed, 164 were found to require cost reductions. At 10 of those sites, more than half of the increases demanded by contractors were rolled back.


lucky@heraldcorp.com