A visit to SK hynix's Yongin semiconductor complex
First fab takes shape, heralding birth of a mega cluster
Vast adjacent site reserved for fabs 2 through 4
Completion date pulled forward by a decade as construction accelerates
About an hour and a half's drive from central Seoul, the general industrial complex of the Yongin semiconductor cluster comes into view — and with it, the first fab SK hynix is building there. The facility is set to become the country's next-generation memory chip production base.
On Tuesday, the site buzzed with thousands of heavy dump trucks and pieces of construction equipment moving in and out without pause. Work pressed on even as temperatures dipped below freezing for the first time this autumn.
After breaking for lunch, workers strapped their hard hats back on and returned to their stations for the afternoon shift. Dozens of massive cranes swung overhead, hoisting materials into place.
Billed as the largest semiconductor investment project in South Korean history, the Yongin cluster's general industrial complex spans 4.15 million square meters — roughly 1.4 times the area of Yeouido.
About 20,000 workers are deployed across the site each day, each assigned to a specific zone. The influx of skilled laborers from across the country has driven up rents for nearby studio apartments, with monthly rent climbing from around 700,000 to 800,000 won ($530 to $600) to as high as 2 million won. New on-site canteens are also being built to feed the growing workforce.
SK hynix plans to invest a total of 600 trillion won ($455 billion) in the Yongin cluster to build four fabs. The company originally planned to complete them sequentially by 2044, but has pulled that deadline forward by a decade to 2034. The decision to accelerate reflects a deepening global memory chip shortage amid an unprecedented semiconductor boom.
The first fab, known as Y1, sits at the northernmost end of the Yongin cluster. Groundbreaking took place in February last year, and 21 months on, the structure stands alone on what was once open land — a harbinger of the mega cluster to come. In the first-phase zone, where the structural framework is complete, workers were busy attaching exterior panels to the outer walls.
The first fab will house six clean rooms in total. SK hynix has moved up the opening of the first clean room by three months, from May 2027 to February 2027. Construction on the second phase of the first fab, which began in April this year, is scheduled to run through June 2028.
Alongside the fab, workers are also building a central utility building to supply heat, a wastewater treatment facility, a structure providing gas and steam, and an underground water reservoir.
To the south of the first fab stretches a vast expanse of open land where fabs 2, 3 and 4 will eventually rise. Excavators were already at work scooping out earth, with dump trucks ferrying the soil away as foundation work got underway.
SK hynix expects demand for memory chips to continue outpacing supply for the foreseeable future. As the AI era matures and demand for advanced semiconductors grows rapidly, the company sees stable production capacity as the decisive competitive edge.
Once all four fabs are complete, the Yongin semiconductor cluster is expected to serve as a strategic hub for South Korea's chip industry, producing AI memory including high-bandwidth memory and high-performance DRAM.